Cement Equipment, Cement Machinery,Cement Production Line
CMHE >> Building Materials Equipment >> Bulk machine >> Pulverized coal ash bulk loader for generating plant

Pulverized coal ash bulk loader for generating plant

Miss Shao : +86-1862762655

TEL: +86-513-88400999 FAX: +86-513-88400998 E-mail: jszk@vip.163.com

 

Pulverized coal dust bulk loader of generating plant is mainly used in bulk loading of powder coal and cement bulk loading in cement plant. Compared with normal bulk loader, it is separated from drawn parts and can improve the driving rate and durability of the equipment. It can be equipped with unloader, conveying air slide, vibration hopper and other automatic feeding bulk loading equipment, ship loading equipment with automatic control system. It works in sealing condition and effectively prevents dust leaking out.

Main structure and working principle
1、Flexible bulk loader
  Flexible bulk loader is composed of driving frame, hoisting structure, driving device, loose wire structure, channel steel pedestal, level meter, dust suction fan, discharge pipe, dust suction pipe and bulk loading head. Material will flow into charging tank through discharge pipe. The dust between discharge pipe and dust suction pipe is discharged into filtering bag or dust silo via dust suction fan. Discharge pipe and dust suction pipe may be flexible. With the help of lifting and falling, the lifting of bulk loading head is done through the driving system of the hoister and its safe control device and loose wire device.
2、Outside lining rubber layer of falling head of dry dust bulk loader is sealed with tank truck closely.
3、The structure of discharge head is of double cone. The discharging opening will be closed automatically after lifting. 
4、Level mater is used the original imported solid tuning fork limit switch with good quality, nimble and dependable characters.  
Main technical parameter
Item
SZJ-100A
SZJ-150A
SZJ-200A
Loading capacity(t/h)
100
150
200
Diameter of discharge pipe Φmm
219
273
325
Diameter of sucking material
400
400
400
Travel of bulk loading head mm
13003000
Lifting and falling speed of bulk loading head
(m/min)
6.6
6.6
6.6
Outline dimensionL×W×Hmm
2286×1050×900
Total weight(t)
0.85
0.9
0.95
Installation and commissioning
1. After installing the equipment, first drive with no load manually: start hoisting device and make bulk loading head fall down and lift. Watch whether it is nimble and stable. Test running goes on the following work:
2.Testing of pulling cord limit switch need make bulk loading head down to the Max. travel. Make bulk loading head and truck tank sealed together. Make bulk loading head down continuously. At this time, steel rope is in loose condition and the pull-cord limit switch will send out signals. 
3. When Bulk loading head is lifted to the regulated hanging position, bulk loading head lifts to final limit switch. Limit switch of hoisting device will send out signals and bulk loading head will stop lifting.

Operation sequence
When the truck is in the right position, half-automatic control device will be used to descend the the bulk loading head. When the bulk loading head is closely connented with the ash inlet of the truck,restart the automatic controlling device. Start the fan automatically and open the upper feeder to feed into the truck. When the charging tank is full, the level switch will feel and give out signals. The relative electric control or pneumatic control will close the feeder automatically. Delay some time (normally 4 to 6 seconds), close the dust suction fan by itself. At last, it will lift the bulk loading head and finish one-time discharging. The feeder and dust suction fan will interlock during feeding and discharging process. That is to say, one action is done, the other one can not be started or stopped. Interlocking must be removed if the sequence need to be disturbed.
matters need attention
The bulk loading head must be aligned with the mouth of the tank when operating. Or there will be flash.
1.During feeding, if there is much dust raising, it means blocking of material. Stop feeding immediately. Do not lift the bulk loading head.
2.If the bulk loading head is down and the steel rope is loose, stop the hoister to prevent accidents. Therefore, when operating, notice that the bulk loading head falls down to the right position without lighted indication light. It means the pull-cord switch is not working, and stop feeding immediately, lift the bulk loading head and do inspection job.
3.If the level meter doesn’t give out when the material is full. Stop feeding immediately and lift the bulk loading head. If the level meter is not working, stop feeding for inspection.
4.If there is flash during feeding, stop it immediately. Do not lift the bulk loading head 5.when the material is full. First take the suction tube preventer down, discharge the storing material and then lift the bulk loading head.
6.If the outlet pipe is not flexible, adjust the length of steel rope to make it flexible.

That may interest you:

Fax:+86-513-88400998 Tel:+86-513-88400999 E-mail:jszk@vip.163.com
Add:Si Jin Industrial Park in Baidian couty, Nantong city, Jiangsu Province,China
© JiangSu China Mining Heavy Equipment Co.,Ltd. BY Tiangen Design
备案号:苏ICP备13032710号-1

SUBORDINATE |CERTIFICATES | Privacy Policy | Sitemap |